Upcoming Construction Activities:
-
-
- Pavement resurfacing for Hueneme Road and Naval Air Road with 2-layer system which includes Asphalt Rubber Hot Mix (w/ fiber reinforcement) over Asphalt Rubber Aggregate Membrane
- Pavement resurfacing for Fifth Street, Doris Ave, Patterson Ave, Channel Islands Blvd, and Rice Ave with Asphalt Concrete Overlay
- Centerline and edge line rumble strips along Hueneme Road
- Drainage improvements on Hueneme Road and Naval Air Road
- New striping enhancements for all roadways
-
Construction – Start in May 2025 and end July 2025
Project Manager: Chase Luckey (805) 654-2050