Coyote Creek Pilot Channel Update

Upcoming Construction Activities

  • September 24 – 27:  Establish Survey Control and Survey Layout.  Vegetation Removal and Dewatering
  • October 7 – November 15:  Debris and Soils Removal, Rough Grading
  • November 15 – 24:  Cleanup, Finish Grading

Construction completion anticipated November 24, 2024