COMPLETED TO DATE
- New 66” storm drain pipe including catch basins installed on Cortez W/O Walnut
- New 36” storm drain pipe including catch basins for Alvarado W/O Walnut
- New curb & gutter, sidewalk, and driveway tie-ins on Stroube (South Side only) between Rose to Jourdan
- New curb & gutter, sidewalk, and driveway tie-ins on Stroube (North Side only) between Jourdan to Cortez
- New infiltration trench installed on Stroube (South Side only) from Rose to Jourdan
- New infiltration trench installed on Stroube (North Side only) from Jourdan to Cortez
- New access ramps at Stroube/Alvarado, Stroube/Balboa, Stroube/Cortez intersections
- Edison utility power pole relocations at Stroube and Walnut
- Gas company utility relocation at Walnut/Alvarado
- Temporary cluster mailboxes
- Fence relocations
Upcoming Construction Activities (through Mid-December)
- Demolition and grading along on Cortez (West Side only) from Orange to Corsicana for new sidewalks
- New curb & gutter, sidewalk, and driveway tie-ins on Cortez (West Side only) from Stroube to Orange
- New curb & gutter, sidewalk, and driveway tie-ins on Cortez (West Side only) from Orange to Corsicana
- New infiltration trench installed on Cortez (West Side only) from Stroube to Collins
- New access ramps at Cortez/Collins, Cortez/Orange, Cortez/Walnut intersection
- Pavement widening on Stroube (North Side only) from Jourdan to Rose
- Pavement widening on Stroube (South Side only) from Jourdan to Cortez
Construction completion anticipated mid-April 2025.